From Mike, the edgy framer, via email.

Moreno

Tasks completed

a.Upper floor framed.
b. windows layed out and 4 completed.
c.Structural issues resolved and lumber ordered.
d.Foundation layout for Adams field observation completed.

Goals for next 2 weeks 
a.Complete the structural beam install.
b. Foundation poured.
c.Fireplace demo completed.
d. Strat framing of new addition.
Mike